Questions from General Operations Management


Q: Construct a network diagram for the information in the following table.

Construct a network diagram for the information in the following table. Use either AOA or AON (see Example 5 for either type). What is the probability that the project will take more than 10 weeks to...

See Answer

Q: The project described in the following table is scheduled to be completed

The project described in the following table is scheduled to be completed in 11 weeks. Construct a network diagram using AOA or AON. Then answer the following questions: a. If you were the manager of...

See Answer

Q: The following precedence diagram reflects three time estimates in weeks for each

The following precedence diagram reflects three time estimates in weeks for each activity. Determine: a. The expected completion time for each path and its variance. b. The probability that the projec...

See Answer

Q: A project manager has compiled a list of major activities that will

A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and pr...

See Answer

Q: Here is a list of activity times for a project as well

Here is a list of activity times for a project as well as crashing costs for its activities. Determine which activities should be crashed and the total cost of crashing if the goal is to shorten the p...

See Answer

Q: Identify the term being described for each of the following:

Identify the term being described for each of the following: a. A sequence of activities in a project. b. The longest time sequence of activities in a project. c. Used when two activities have the sam...

See Answer

Q: The project manager of a task force planning the construction of a

The project manager of a task force planning the construction of a domed stadium had hoped to be able to complete construction prior to the start of the next college football season. After reviewing c...

See Answer

Q: A construction project has indirect costs totaling $40,000 per

A construction project has indirect costs totaling $40,000 per week. Major activities in the project and their expected times in weeks are shown in this precedence diagram. Crashing costs for each a...

See Answer

Q: Chuck’s Custom Boats (CCB) builds luxury yachts to customer order

Chuck’s Custom Boats (CCB) builds luxury yachts to customer order. CCB has landed a contract with a mysterious New York lawyer (Mr. T). Relevant data are shown on the next page. The...

See Answer

Q: What is the ultimate goal of a lean system? What are

What is the ultimate goal of a lean system? What are the supporting goals? What are the building blocks?

See Answer