Questions from General Operations Management


Q: An architect has five projects to complete. She estimates that three

An architect has five projects to complete. She estimates that three of the projects will require one week to complete and the other two will require three weeks and four weeks. During the time these...

See Answer

Q: Given the projects displayed in Table 11.15, assume FCFS

Given the projects displayed in Table 11.15, assume FCFS is used to sequence the jobs. a. What is the average flow rate of the projects (in projects per hour)? [11.2] b. What is the average flow time...

See Answer

Q: Assume the jobs displayed in Table 11.17 need to be

Assume the jobs displayed in Table 11.17 need to be processed on a single resource and are sequenced with the WSPT rule. Which job would be processed third? [11.3]

See Answer

Q: Strohrmann, a large-scale bakery in Pennsylvania, is laying

Strohrmann, a large-scale bakery in Pennsylvania, is laying out a new production process for their packaged bread, which they sell to several grocery chains. It takes 12 minutes to bake the bread. How...

See Answer

Q: There are five planes ready for departure at an airport. The

There are five planes ready for departure at an airport. The number of passengers on each plane is displayed in Table 11.18. Each plane requires 10 minutes to taxi to the runway and 2 minutes to take...

See Answer

Q: If the jobs displayed in Table 11.20 are processed using

If the jobs displayed in Table 11.20 are processed using the earliest-due-date rule, a. What would be the lateness of job B? [11.4] b. What would be the tardiness of job E? [11.4] c. What is the maxim...

See Answer

Q: Consider the dependency matrix and the activity durations provided above.

Consider the dependency matrix and the activity durations provided above. a. Build a project graph, visually depicting the evolution of this project. [12.2] b. Find the critical path. What is the earl...

See Answer

Q: Thierry, Ute, and Vishal are getting ready for their last

Thierry, Ute, and Vishal are getting ready for their last period in the MBA program. Following the final exams, they intend to throw a big party with many of their friends from back home. Presently, t...

See Answer

Q: A small project consists of three activities: A, B,

A small project consists of three activities: A, B, and C. To start activity C, both activities A and B need to be complete. Activity A takes 3 days with a probability of 50 percent and 5 days with a...

See Answer

Q: Jim and John run a barber shop. Every night, both

Jim and John run a barber shop. Every night, both of them predict how many guests will come on the next day. Over the last four days, they have collected some data about their predictions and the actu...

See Answer