Questions from General Project Management


Q: Assume you are a member of a class on project management.

Assume you are a member of a class on project management. Each student will join a team of 5–7 students who will be responsible for creating, planning, and executing a fund raising p...

See Answer

Q: Scanner Project You have been serving as Electroscan’s project manager and are

Scanner Project You have been serving as Electroscan’s project manager and are now well along in the project. Develop a narrative status report for the board of directors of the chai...

See Answer

Q: Wil Fence is a large timber and Christmas tree farmer who is

Wil Fence is a large timber and Christmas tree farmer who is attending a project management class in the spring, his off season. When the class topic came to earned value, he was perplexed. Isn’t he u...

See Answer

Q: The following labor hours data have been collected for a nanotechnology project

The following labor hours data have been collected for a nanotechnology project for periods 1 through 6. Compute the SV, CV, SPI, and CPI for each period. Plot the EV and the AC on the summary graph p...

See Answer

Q: The following data have been collected for a British health care IT

The following data have been collected for a British health care IT project for two week reporting periods 2 through 12. Compute the SV, CV, SPI, and CPI for each period. Plot the EV and the AC on the...

See Answer

Q: * Part A. You are in charge of the Aurora Project

* Part A. You are in charge of the Aurora Project. Given the following project network, baseline, and status information, develop status reports for periods 1–8 and complete the perf...

See Answer

Q: Given the project network and baseline information below, complete the form

Given the project network and baseline information below, complete the form to develop a status report for the project at the end of period 4 and the end of period 8. From the data you have collected...

See Answer

Q: Given the following project network, baseline, and status information,

Given the following project network, baseline, and status information, develop status reports for periods 2, 4, 6, 8 and complete the performance indexes table. Calculate the EACf and the VACf. Based...

See Answer

Q: What are the differences between BAC and EAC?

What are the differences between BAC and EAC?

See Answer

Q: Why is it important for project managers to resist changes to the

Why is it important for project managers to resist changes to the project baseline? Under what conditions would a project manager make changes to a baseline? When would a project manager not allow cha...

See Answer