Questions from General Project Management


Q: You are creating a customer database for the Hillsboro Hops minor league

You are creating a customer database for the Hillsboro Hops minor league baseball team. Draw a project network given the information in the table that follows. Complete the forward and backward pass,...

See Answer

Q: K. Nelson, project manager of Print Software, Inc.,

K. Nelson, project manager of Print Software, Inc., wants you to prepare a project network; compute the early, late, and slack activity times; determine the planned project duration; and identify the...

See Answer

Q: A large Southeast city is requesting federal funding for a park-

A large Southeast city is requesting federal funding for a park-and-ride project. One of the requirements in the request application is a network plan for the design phase of the project. Sophie Kim,...

See Answer

Q: You are creating a database for the Oklahoma City Thunder NBA

You are creating a database for the Oklahoma City Thunder NBA Basketball team. Given the project network that follows, complete the forward and backward pass, compute activity slack, and identify th...

See Answer

Q: You have prepared the following schedule for a project in which the

You have prepared the following schedule for a project in which the key resource is a backhoe(s). This schedule is contingent on having 3 backhoes. You receive a call from your partner, Brooker, who d...

See Answer

Q: Given the following information, compute the early, late,

Given the following information, compute the early, late, and slack times for the project network. Which activities on the critical path have only the start or finish of the activity on the critical...

See Answer

Q: Given the network below, compute the early, late, and

Given the network below, compute the early, late, and slack time for each activity. Clearly identify the critical path.

See Answer

Q: Draw a project network from the following information. What activity

Draw a project network from the following information. What activity (ies) is a burst activity? What activity (ies) is a merge activity?

See Answer

Q: Draw a project network from the following information. What activity (

Draw a project network from the following information. What activity (ies) is a burst activity? What activity (ies) is a merge activity?

See Answer

Q: From the following information, develop an AON project network. Complete

From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take?

See Answer