Questions from Geotechnical Engineering


Q: Refer to the cross section of the earth dam shown in

Refer to the cross section of the earth dam shown in Figure 8.19. Calculate the rate of seepage through the dam (q in m3/min/m) using Schaffernak’s solution.

See Answer

Q: Solve Problem 8.10 using L. Casagrande’s method.

Solve Problem 8.10 using L. Casagrande’s method.

See Answer

Q: An earth dam section is shown in Figure 8.33.

An earth dam section is shown in Figure 8.33. Determine the rate of seepage through the earth dam using Pavlovsky’s solution. Use k = 4 × 10-5 mm/s.

See Answer

Q: Draw a flow net for the single row of sheet piles driven

Draw a flow net for the single row of sheet piles driven into a permeable layer as shown in Figure 8.28. Given: H1 = 3 m D = 1.5 m H2 = 0.5 m D1 = 3.75 m Calculate the seepage loss per meter le...

See Answer

Q: Refer to Figure 8.28. Given: H1 =

Refer to Figure 8.28. Given: H1 = 4 m D1 = 6 m H2 = 1.5 m D = 3.6 m Calculate the seepage loss in m3/day per meter length of the sheet pile (at right angles to the cross section shown). Use Figure...

See Answer

Q: The porosity of a soil is 0.35. Given Gs

The porosity of a soil is 0.35. Given Gs = 2.69, calculate: Saturated unit weight (kN/m3 ) Moisture content when moist unit weight 5 17.5 kN/m3

See Answer

Q: For the hydraulic structure shown in Figure 8.29, draw

For the hydraulic structure shown in Figure 8.29, draw a flow net for flow through the permeable layer and calculate the seepage loss in m3 /day/m.

See Answer

Q: Refer to Problem 8.4. Using the flow net drawn

Refer to Problem 8.4. Using the flow net drawn, calculate the hydraulic uplift force at the base of the hydraulic structure per meter length (measured along the axis of the structure).

See Answer

Q: Draw a flow net for the weir shown in Figure 8.

Draw a flow net for the weir shown in Figure 8.30. Calculate the rate of seepage under the weir.

See Answer

Q: For the weir shown in Figure 8.31, calculate the

For the weir shown in Figure 8.31, calculate the seepage in the permeable layer in m3/day/m for x9 = 1 m and x9 = 2 m. Use Figure 8.13.

See Answer