2.99 See Answer

Question: The MRP gross requirements for item X

The MRP gross requirements for item X are shown here for the next 10 weeks. Lead time for A is two weeks, and setup cost is $9. There is a carrying cost of $0.02 per unit per week. Beginning inventory is 70 units.
The MRP gross requirements for item X are shown here for the next 10 weeks. Lead time for A is two weeks, and setup cost is $9. There is a carrying cost of $0.02 per unit per week. Beginning inventory is 70 units.


Use the least total cost or the least unit cost lot-sizing method to determine when and for what quantity the first order should be released. (Answer in Appendix D)
Use the least total cost or the least unit cost lot-sizing method to determine when and for what quantity the first order should be released. (Answer in Appendix D)





Transcribed Image Text:

Week 1 2 4 6 7 8 10 Gross requirements 20 10 15 45 10 30 100 20 40 150 LO


> What term refers to a schedule that pulls material into final assembly at a constant rate?

> Bill Edstrom, managing partner at a biomedical consulting firm, has requested your expert advice in devising the best schedule for the following consulting projects, starting on February 2. The consulting firm charges a flat rate of $4,000 per day. All

> The following table contains information regarding jobs that are to be scheduled through one machine. a. What is the first-come, first-served (FCFS) schedule? b. What is the shortest operating time (SOT) schedule? c. What is the slack time remaining (S

> A manufacturing facility has five jobs to be scheduled into production. The following table gives the processing times plus the necessary wait times and other necessary delays for each of the jobs. Assume that today is April 3, that the facility will wor

> What do we generally call an area in a business where productive resources are organized and work is completed?

> What is the term used for an information system that links, schedules, dispatches, tracks, monitors, and controls customer encounters with a service organization?

> Which simple scheduling concept can be applied to help schedule workers for service operation with changing staffing requirements throughout the day?

> What feature of manufacturing planning and control systems operates under the premise that planned work input to a work center should never exceed the planned work output?

> What shop-floor control document tells the supervisor which jobs are to be run, in what order, how long each will take?

> Distinguish between in-process inventory, safety stock inventory, and seasonal inventory.

> A company has a factory that is designed so that it is most efficient (average unit cost is minimized) when producing 15,000 units of output each month. However, it has an absolute maximum output capability of 17,250 units per month, and can produce as

> Which graphical tool commonly used in project management is also very useful in shop-floor control?

> What lean concept relates to eliminating non-value-added steps and waste in product storage processes?

> A psychological therapist treats patients according to their individual needs. Patients are all treated in the same office on a scheduled basis. Each patient’s treatment is customized for the individual according to the therapist’s professional trainin

> What is another common term for shop-floor control?

> A key part of work-center scheduling is job sequencing – deciding in what order jobs are scheduled to start/complete. What is the term for the simple rules used to aid this process using a single bit of data about the jobs?

> What type of inventory are we trying to minimize as the result of work-center scheduling?

> If you have five exams to study for, how many alternative schedules exist?

> What priority rule do you use in scheduling your study time for midterm examinations?

> What practical considerations are deterrents to using the SOT rule?

> Meritor is so pleased with the outcome from previous suggestions that the consultants are invited back for more work. The consultants now suggest a more complete robotic automation of the making of muffler assemblies and also a reduction in container siz

> How might planning for a special customer affect the personnel schedule in a service?

> Explain why scheduling personnel in a service operation can be challenging.

> Data integrity is a big deal in industry. Why?

> The following represents a project that should be scheduled using CPM: a. Draw the network. b. What is the critical path? c. What is the expected project completion time? d. What is the probability of completing this project within 16 days? TIMES (

> Suppose that operators have enough training to operate both the bronze machines and the injection molding machine for the plastic sprinklers. Currently, AlwaysRain has 10 such employees. In anticipation of the ad campaign described in problem 5, manageme

> Flowcharts are a common process design and analysis tool used in both manufacturing and services. What is a key feature on flowcharts used in service operations that differentiates between the front-office and back-office aspects of the system?

> How would a flowchart help in planning the servicescape layout? What sorts of features would act as focal points or otherwise draw customers along certain paths through the service? In a supermarket, what departments should be located first along the c

> Why is it desired to have smooth, continuous flow on the shop floor?

> The chapter discusses the use of Gantt charts in shop floor control. You were introduced to Gantt charts in Chapter 4, “Project Management.” Projects and workcenter processes are rather different in nature. Why is it that the same tool can be used in bot

> Under what conditions is the assignment method appropriate?

> Distinguish between dependent and independent demand in a McDonald’s, in an integrated manufacturer of personal copiers, and in a pharmaceutical supply house.

> Why is managing bottlenecks so important in workcenter scheduling?

> What job characteristics would lead you to schedule jobs according to “longest processing time first”?

> Why does batching cause so much trouble in workcenters?

> The SOT rule provides an optimal solution in a number of evaluation criteria. Should the manager of a bank use the SOT rule as a priority rule? Why?

> List at least four of the seven prominent types of waste that should be eliminated from the supply chain.

> Distinguish between a work center, a GT cell, and an assembly line.

> What are the objectives of work-center scheduling?

> Good doctor–patient relations begin with both parties being punctual for appointments. I am Dr. Schafer, and being punctual is particularly important in my specialty: pediatrics. Mothers whose children have only minor problems don’t like them to sit in

> An important difference between service and manufacturing operations is that customers induce far more variability into the operation in a service system. Name at least three of the basic types of variation that customers bring to a service system.

> In anticipation of the ad campaign, AlwaysRain bought an additional bronze machine. Will this be enough to ensure that adequate capacity is available?

> What are some capacity balance problems faced by the following organizations or facilities? a. An airline terminal b. A university computing lab c. A clothing manufacturer

> Assume that product Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E. Lead times for the purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and

> In the following MRP planning schedule for item J, indicate the correct net requirements, planned-order receipts, and planned-order releases to meet the gross requirements. Lead time is one week. Week Number Item J 2 3 4 Gross requirements 75 50 70

> Semans is a manufacturer that produces bracket assemblies. Demand for bracket assemblies (X) is 130 units. The following is the BOM in indented form: The following is a table indicating current inventory levels: a. Using Excel, create the MRP using t

> Match the industry type to the expected benefits from an MRP system as High, Medium, or Low. Industry Type Expected Benefit (High, Medium, or Low) Assemble-to-stock Assemble-to-order Make-to-stock Make-to-order Engineer-to-order Proce

> Product A consists of two units of subassembly B, three units of C, and one unit of D. B is composed of four units of E and three units of F. C is made of two units of H and three units of D. H is made of five units of E and two units of G. a. Construct

> What term refers to the optimization of value-adding activities and elimination of non-value adding activities that are part of a value stream?

> The MRP gross requirements for item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost is $10. There is a carrying cost of $0.01 per unit per week. Beginning inventory is 90 units. Use the least total cost or the leas

> Audio Products, Inc., produces two AM/FM/CD players for cars. The radio/CD units are identical, but the mounting hardware and finish trim differ. The standard model fits intermediate and full-sized cars, and the sports model fits small sports cars.

> Product A is an end item and is made from two units of B and four of C. B is made of three units of D and two of E. C is made of two units of F and two of E. A has a lead time of one week. B, C, and E have lead times of two weeks, and D and F have lead t

> How have price and variety competition changed McDonald’s basic formula for success?

> As the degree of customer contact increases in a service system, what worker skills would be more important, clerical skills or diagnostic skills?

> Each unit of A is composed of one unit of B, two units of C, and one unit of D. C is composed of two units of D and three units of E. Items A, C, D, and E have on-hand inventories of 20, 10, 20, and 10 units, respectively. Item B has a scheduled rece

> Suppose that AlwaysRain Irrigation’s marketing department will undertake an intense ad campaign for the bronze sprinklers, which are more expensive but also more durable than the plastic ones. Forecast demand for the next four years is

> One unit of A is composed of two units of B and three units of C. Each B is composed of one unit of F. C is made of one unit of D, one unit of E, and two units of F. Items A, B, C, and D have 20, 50, 60, and 25 units of on-hand inventory, respectivel

> One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; items A, B,

> One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; items A, B, E, and F ha

> What phrase refers to the idea that every step in supply chain processes that deliver goods and services to the customer should create value?

> What is value stream mapping?

> One unit of A is made of two units of B, three units of C, and two units of D. B is composed of one unit of E and two units of F. C is made of two units of F and one unit of D. E is made of two units of D. Items A, C, D, and F have one-week lead times; B

> One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A a

> Consider a department store. Which departments probably should not be located near each other? Would any departments benefit from close proximity?

> Big10Sweaters.com is a new company started last year by two recent college graduates. The idea behind the company was simple. It will sell premium logo sweaters for Big Ten colleges with one major, unique feature. This unique feature is a special large m

> What category of planning covers a period from a day to six months, with daily or weekly time increments?

> Major operations and supply planning activities can be grouped into categories based on the relevant time range of the activity. What time range category does sales and operations planning fit into?

> What strategy do the following organizations seem to use to manage customer-introduced variability? a. EBay b. Ritz-Carlton Hotels c. New airline check-in procedures

> List some practical limits to economies of scale; that is, when should a plant stop growing?

> The essence of yield management is the ability to manage what?

> In a yield management system, pricing differences must appear logical and justified to the customer. The basis for this justification is commonly called what?

> Under what type of demand is yield management most effective?

> The widespread scientific application of yield management began within what industry?

> Refer to Example 14.1 as the basis for this problem. Meritor hires a team of consultants. The consultants suggest a partial robotic automation, as well as an increase in safety stock to 12.5 percent. Meritor implements these suggestions. The result is an

> How would you show a pull system in VSM Symbols between the blanking and CNC stages of the bolt manufacturing solved problems?

> Which of the four costs relevant to aggregate production planning is the most difficult to accurately measure?

> List at least three of the four costs relevant to the aggregate production plan.

> What is the term for a more complex production strategy that combines approaches from more than one basis strategy?

> In the agriculture industry, migrant workers are commonly employed to pick crops ready for harvest. They are hired as needed and are laid off once the crops are picked. This approach is made necessary by the realities of the industry. Which production p

> Plan production for the next year. The demand forecast is: spring, 20,000; summer, 10,000; fall, 15,000; winter, 18,000. At the beginning of spring you have 70 workers and 1,000 units in inventory. The union contract specifies that you may lay off work

> Suppose you were the manager of a restaurant and you were told honestly that a couple eating dinner had just seen a mouse. What would you say to them? How would you recover from this service crisis?

> Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers

> What capacity problems are encountered when a new drug is introduced to the market?

> Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 10,000; winter, 8,000; spring, 7,000; summer, 12,000. Inventory at the beginning of fall is 500 units. At the beginning of fall, you currently have 30 worke

> Helter Industries, a company that produces a line of women’s bathing suits, hires temporaries to help produce its summer product demand. For the current four-month rolling schedule, there are three temps on staff and 12 full-time employ

> A bottling plant fills 2,400 bottles every two hours. The lead time is 40 minutes and a container accommodates 120 bottles. The safety stock is 10 percent of expected demand. How many kanban cards are needed?

> Develop a production schedule to produce the exact production requirements by varying the workforce size for the following problem. Use the example in the chapter as a guide (Plan 1). The monthly forecasts for Product X for January, February, and March a

> Shoney Video Concepts produces a line of video streaming servers that are linked to computers for storing movies. These devices have very fast access and large storage capacity. Shoney is trying to determine a production plan for the next 12 months.

> Alan Industries is expanding its product line to include three new products: A, B, and C. These are to be produced on the same production equipment, and the objective is to meet the demands for the three products using overtime where necessary. The deman

> Old Pueblo Engineering Contractors creates six-month “rolling” schedules, which are recomputed monthly. For competitive reasons (it would need to divulge proprietary design criteria, methods, and so on), Old Pueblo

> DAT, Inc., needs to develop an aggregate plan for its product line. Relevant data are The forecast for next year is Management prefers to keep a constant workforce and production level, absorbing variations in demand through inventory excesses and sh

> In what way does the time horizon chosen for an aggregate plan determine whether it is the best plan for the firm?

> Can a manufacturer have a service guarantee in addition to a product guarantee?

> What are the major differences between aggregate planning in manufacturing and aggregate planning in services?

> How would you apply yield management concepts to a barbershop? A soft drink vending machine?

> Refer to Exhibit 5.6. Why is it that the “critical zone” begins at a utilization rate of about 70 percent in a typical service operation? Draw upon your own experiences as either a customer or a server in common serv

> Transmissions are delivered to the fabrication line four at a time. It takes one hour for transmissions to be delivered. Approximately four vehicles are produced each hour, and management has decided that 50 percent of expected demand should be maintaine

> Define yield management. How does it differ from the pure strategies in production planning?

> What are the basic controllable variables of a production planning problem? What are the four major costs?

> How does forecast accuracy relate, in general, to the practical application of the aggregate planning models discussed in the chapter?

2.99

See Answer